Work on the Berkut platform

Berkut — offshore drilling rig

Russia's largest offshore oil and gas drilling platform designed for the development of Arkutun Dagi, the third field of the project "Sakhalin-1". The platform is located 25 kilometers from the northern part of Sakhalin Island, offshore in the Sea of Okhotsk.

Customer: SMNG "Shelf"


Working periodDescription of worksResults
October 2024Maintenance of AMS 900LH generators
• Equipment:
— DSU essential (2 pcs.), emergency (1 pc.)
— Frequency converters ABB ACS800 (2 pcs.)
• Accomplished work:
✔ Diagnostics of the generators' condition
✔ Checking the IF parameters
✔ Delivery of spare parts under the L3 program
Uninterrupted operation of the platform's power system during the autumn-winter period has been ensured
October 2024Calibration of ABB and GE relay protection
• Equipment:
— ABB terminals REM 543, REM 545
— GE Multilin RELAY 869, 469
— VD4 switches
Accomplished work:
✔ Checking the input circuits
✔ Testing the trigger logic
The correct operation of the security systems has been confirmed
February 2025Maintenance of ABB Emax switches
• Equipment:
— ABB Emax circuit breakers (31 units)
Accomplished work:
✔ Checking of mechanical characteristics
✔ Measurement of insulation resistance
Reliable switching in winter conditions is ensured

Do you have a need to carry out such work or do you have other specialized tasks?

Our experts will respond as soon as possible!